Project Background

Customer Requirements:
The city's newly built energy integrated management and control center needs to build a core command screen system to monitor key data such as power grid load, oil and gas pipeline pressure, and water source scheduling in real time. The project requires 24/7 uninterrupted operation, supports simultaneous visualization of 12 heterogeneous system signals (SCADA/GIS/video surveillance, etc.), and realizes cross-departmental collaborative command in the event of emergencies.

Project Challenge:
  • Ultra-Long Standby Requirements: annual average operation ≥ 8,000 hours, must meet 100,000 hours of life design;
  • Multi-Signal Compatibility: three sets of isolated network signals of power network/government network/Internet need to be integrated;
  • Strong Light Interference: the control room has one surrounding window, and the ambient illumination is as high as 1,500 lux;
  • Ergonomic Defects: the original layout caused 30% of the seats to have blind spots in the screen viewing angle.

Solution

1

Display System Customization:

  • Select indoor SMD small-pitch screen (P1.25mm), 3840Hz refresh rate to eliminate high-speed data flow smear;
  • The cabinet is equipped with an independent air duct cooling system to ensure stable operation in a high-temperature environment of 55℃;
  • The modular design supports hot-swap maintenance, and a single cabinet replacement takes ≤5 minutes.
2

Optical Enhancement Processing:

  • Adopt 2500cd/㎡ high-brightness panel + wide viewing angle technology (horizontally/vertically 160°);
  • Load intelligent light sensing algorithm to dynamically adjust contrast according to the intensity of sunlight outside the window;
  • Add anti-glare AG glass on the surface to reduce strong reflection interference.
3

Signal System Integration:

  • Deploy a fiber-optic KVM seat management system to enable 12 seats to call up signal sources at will;
  • Configure a dual-engine processor (automatic master-slave switching) to support 4K@60Hz lossless transmission;
  • Establish a three-layer security isolation: physical network gate + protocol filtering + permission authentication.
4

Space Optimization Layout:

  • 15° arc splicing (radius 8m) is used to eliminate the viewing angle deviation of the edge seats;
  • The bottom of the screen is raised 1.2m to ensure unobstructed viewing distance for people in the back row;
  • The pre-buried cable duct integrates 200+ cables and has passed the TIA-942 equipment room certification.

Project Outcomes

  • A 10.24m×3.84m curved large screen (64 cabinets) was built, with an average daily operation of 18.5 hours;
  • Multi-signal switching delay <0.2 seconds, emergency response efficiency increased by 40%;
  • Zero downtime within a two-year operation cycle, pixel failure rate <0.01%;
  • Energy consumption control reached 1.8W/thousand pixels, and obtained LEED Energy Star certification;
  • Operator visual fatigue complaint rate decreased by 73%.
Image

Project Highlights:

Millisecond Response: ≤800ms from SCADA alarm to large screen pop-up window;

Cross-segment Penetration: realize three-network signal linkage without breaking network isolation;

Intelligent Operation and Maintenance: AI diagnosis system predicts fault module 48 hours in advance;

Ultra-Wide Color Gamut: 115% NTSC coverage accurately restores pipeline heat map;

Zero Blue Light Damage: passed TÜV Rheinland low blue light certification.

Project Summary

This project built a smart command center based on small-pitch LEDs for an energy control center in South America. Through a high-reliability display system, multi-network fusion signal architecture, and ergonomic optimization design, it successfully solved core problems such as 7×24-hour monitoring, visibility in strong light environments, and cross-segment data collaboration. After the project was put into operation, it became the core platform for regional energy dispatching, and the two-year trouble-free operation record verified the maturity of the industrial-grade display solution.

Date

29 May 2025

Tags

Control Room

Let’s Talk!

We are committed to promoting education and business development by providing professional hardware and software, providing solutions based on personalized needs.
Image
Sign Up for Newsletter
Stay updated with the latest insights, tips, and success stories from our team.
Quick Links
Contact Us

Email: info@wiliang.com

Whatsapp:+86 19926823136

Address:3rd Floor, Building 7, Skyworth Innovation Valley, Baoan District, Shenzhen, China 518101